(Ten points). (Calculation of net present value) Dowling Sportswear is proposing the construction of a new factory to manufacture aluminum baseball bats. This project would cost a $4,000,000 initial capital outlay and would generate $900,000 in yearly net cash inflows over the next seven years. Determine the project's net present value (NPV) using a 5% discount rate. (Roughly round to the closest $1.)

a. If the discount rate is 5%, the project's net present value is: $ (3,360,387)

Question number two: (30 points). (Net present value calculation) Big Steve's, makers of swizzle sticks, is considering the purchase of a new plastic stamping machine. This investment requires an initial outlay of $90,000 and will generate net cash inflows of $19,000 per year for 11 years. To answer Choose an item questions, click on the orange text and use the pull down menu to select the best answer.

a. What is the project's NPV using a discount rate of 7 percent? (Round to the nearest dollar.)

If the discount rate is 7 percent, then the project's NPV is: $(47242)

Should the project be accepted? No. NPV is negative.

The project should not be accepted because the NPV is negative and therefore subtracts value to the firm.

b. What is the project's NPV using a discount rate of 16 percent?

If the discount rate is 16 percent, then the project's NPV is: $ (72412.479)

Should the project be accepted? Why or why not?

c. What is this project's internal rate of return? (Round to two decimal places.)

This project's internal rate of return is: 10.84 %

Should the project be accepted? Why or why not?

If the project's required discount rate is 7%, then the project should be accepted because the IRR is higher than the required discount rate.

If the project's required discount rate is 16%, then the project should not be accepted because the IRR is lower than the required discount rate.

Question 3: (15 points). (Related to Checkpoint 11.2) (Equivalent annual cost calculation) Barry Boswell is a financial analyst for Dossman Metal Works, Inc. and he is analyzing two alternative configurations for the firm's new plasma cutter shop. The two alternatives that are denoted A and B below perform the same task and although they each cost to purchase and install they offer very different cash flows. Alternative A has a useful life of 7 years whereas Alternative B will only last for 3 years. The after-tax cash flows from the two projects are as follows:

a. Calculate each project's equivalent annual cost (EAC) given a discount rate of 10 percent. (Round to the nearest cent.)

a. Alternative A's equivalent annual cost (EAC) at a discount rate of 10% is: $ 38514.80

b. Alternative B's equivalent annual cost (EAC) at a discount rate of 10% is $ 43204.80

b. Which of the alternatives do you think Barry should select? Why? (Select the best choice below.)

This cannot be determined from the information provided.

Alternative B should be selected because its equivalent annual cost is less per year than the annual equivalent cost for Alternative A.

Alternative A should be selected because its equivalent annual cost is less per year than the annual equivalent cost for Alternative B.

Alternative A should be selected because it has the highest NPV.

Question 4: (10 points). (IRR calculation) What is the internal rate of return for the following project: An initial outlay of $9,000 resulting in a single cash inflow of $15,424 in 7 years. (Round to the nearest whole percent.)

a. The internal rate of return for the project is: 8.00%

Question 5: (10 points). (IRR calculation) Jella Cosmetics is considering a project that costs $750,000 and is expected to last for 9 years and produce future cash flows of $180,000 per year. If the appropriate discount rate for this project is 17 percent, what is the project's IRR? (Round to two decimal places.)

a. The project's IRR is: 18.98%

Question 6: (10 points) (IRR, payback, and calculating a missing cash flow) Mode Publishing is considering a new printing facility that will involve a large initial outlay and then result in a series of positive cash flows for four years. The estimated cash flows associated with this project are:

If you know that the project has a regular payback of 2.9 years, what is the project's internal rate of return?

a. The IRR of the project is: 29.61%

Question 7: (15 points) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows:

If the appropriate discount rate on these projects is 11 percent, which would be chosen and why? (Round to the nearest cent.)

a. The NPV of Project A is: $ 876.91

b. The NPV of Project B is: $ $14,624.78

Which project would be chosen and why? (Select the best choice below.)

Cannot choose without comparing their IRRs

Choose A because its NPV is higher.

Choose both because they both have positive NPVs.

Choose B because its NPV is higher.

June 12, 2023
Category:

Business Economics

Number of pages

3

Number of words

784

Downloads:

58

Writer #

Rate:

4.8

Expertise Construction
Verified writer

I enjoyed every bit of working with Krypto for three business tasks that I needed to complete. Zero plagiarism and great sources that are always fresh. My professor loves the job! Recommended if you need to keep things unique!

Hire Writer

This sample could have been used by your fellow student... Get your own unique essay on any topic and submit it by the deadline.

Eliminate the stress of Research and Writing!

Hire one of our experts to create a completely original paper even in 3 hours!

Hire a Pro

Similar Categories